Building safety

Calls for research centre to stop certifying MMC post-Grenfell

Houses-of-Parliament-300x200.jpg

Peers have called for the Building Research Establishment (BRE) to be stripped of responsibility for certifying modern methods of construction (MMC), following criticism in the Grenfell Inquiry’s final report. A House of Lords debate on MMC yesterday (5 September) also heard calls from across the political spectrum for the BRE…

LABC ‘wholeheartedly’ apologises for Grenfell failures

Grenfell tributes CC by 2.0 credit ChiralJon

A building control body criticised in the Grenfell Inquiry’s final report has “wholeheartedly” acknowledged and apologised for failures of oversight. Yesterday’s report said that Local Authority Building Control (LABC), which represents local authority building inspectors, had failed to ensure certificates issued for products used in building work were technically accurate.…

Scotland presses ahead with building safety levy

Scottish-Parliament-building-in-Holyrood-Edinburgh-scaled-e1725536651515-300x200.jpg

The Scottish government is pressing ahead with plans to introduce a building safety levy. In line with legislation that will be introduced for England and Wales, developers will have to pay towards the cost of remediating dangerous buildings. The legislation was among the bills included in the government programme announced…

Starmer pledges moves to speed up cladding remediation

Keir-Starmer_PMQs_CREDIT-UK-Parliament_Jessica-Taylor-300x200.jpg

Prime minister Keir Starmer today pledged to reform the construction products industry and bring forward measures to speed up remediation of buildings with dangerous cladding, in response to the Grenfell Inquiry phase two report. Addressing Parliament, Starmer said that the government would formally respond to the recommendations made in the…

Grenfell Inquiry panel member: construction must own culture change

EDITORIAL-ONLY_Grenfell_shutterstock_1244543428-1-300x200.jpg

Everyone in construction must play their part in implementing the Grenfell Inquiry's recommendations, according to one of the panel members in an address aimed at the sector. Members of the inquiry panel, including inquiry chair Sir Martin Moore-Bick, spoke about the lessons from their report at a session this morning.…

Grenfell manufacturers respond to inquiry criticisms

EDITORIAL-ONLY_Grenfell_shutterstock_2501880511-300x200.jpg

The three manufacturers of cladding and insulation criticised by the Grenfell Inquiry have responded to the official inquiry’s findings, with one maintaining its product was safe. Kingspan, Arconic and Celotex all set out detailed statements about their products following this morning’s release of the phase two report of the official…

Construction industry shake-up recommended by Grenfell Inquiry report

Building-inspector_surveyor_building-control_shutterstock-300x200.jpg

Contractors working on higher-risk buildings should be licensed, with the system overseen by a new construction regulator, according to the official inquiry into the Grenfell Tower fire. The second phase report by Sir Martin Moore-Bick, published this morning (4 September), made a series of recommendations that would significantly impact the…

‘Serious and longstanding failures’: The role of government and regulators in Grenfell fire

Whitehall

Failures at the top of government and among regulators allowed dangerous new forms of cladding onto the market, according to the Grenfell Tower Inquiry's second phase report. The report, published today (4 September) said that there were “serious and longstanding” failings at the highest level of government. Central government “We…

‘Casual and complacent’: Grenfell report’s damning verdict on Rydon

Grenfell-300x200.jpg

A litany of failures by Rydon, the principal contractor on the Grenfell Tower refurbishment, means it bears “considerable responsibility” for the fatal 2017 blaze, according to the phase two inquiry report. The report, released today (4 September), criticised numerous failings by the company, saying these had significantly contributed to the…

Harley Facades: The role of the cladding subcontractor in Grenfell fire

Grenfell-300x200.jpg

Cladding subcontractor Harley Facades “failed in many respects to meet the standards expected of a reasonably competent cladding contractor”, the Grenfell Inquiry phase 2 report said today. Harley did not have a formal contract to work on the refurbishment of the tower, so its exact legal responsibilities are murky. However,…